Company Announcement: Gindalbie provides Karara Operational Update
Gindalbie Metals Limited advises that the ramp-up of the Karara Project in Western Australia is continuing to progress with no material issues encountered with the commissioning of the plant.
Karara Concentrator
As advised previously, commissioning of the Karara Concentrator is being undertaken in stages with commissioning of seven of nine key areas complete. These include the major components of the critical front-end crushing and grinding circuit of the plant – the primary and secondary crushers, high pressure grinding rolls (HPGRs) and ball mills. All of these components have now been commissioned and have successfully operated at up to their design throughput rate. The project team is currently focusing on commissioning the final two remaining areas – the polishing circuit and a group of ancillary functions including the tailings circuit. Two thirds of the polishing circuit has been commissioned and is operational, resulting in initial improvements to the magnetite concentrate grade up to 65% Fe. The final concentrate grade of 68% Fe is expected to be achieved with the commissioning of the flotation circuit.
After the initial ramp-up of the plant to 70% production throughput capacity, some relatively minor filtering problems have been encountered with the tailings circuit which have temporarily restricted plant throughput. To overcome these issues, a troubleshooting process was undertaken which identified an immediate resolution through the installation of additional piping and pumping capacity. The necessary additional equipment has been ordered and the rectification work will be progressively completed during the second half of June 2013. The project team is targeting to achieve nameplate capacity of 8Mtpa and premium concentrate specifications in July 2013, subject to the timely installation of the new equipment and in the absence of further issues.
57 Shipments Completed
Product shipments are continuing and the Karara Project has now shipped 3.4 million tonnes through the Karara Export Terminal in Geraldton. 46 shipments of DSO hematite have been completed for a total of 2.7 million tonnes. 11 shipments of magnetite concentrate have been completed for a total of 700,000 tonnes.
Funding Update
As the project has not achieved commercial production levels or been declared cash-flow positive, the slower-than-expected shipping schedule will have an impact on the forecast working capital requirements of the joint venture company Karara Mining Limited (KML). KML is currently working on a number of potential funding solutions to assist with short-term working capital requirements. KML has completed a $US44 million magnetite concentrate pre-payment agreement with Ansteel and is working to progress further prepayment agreements. KML has also started discussions regarding a potential restructure of its debt repayment schedule.
Management Comment
Gindalbie’s Managing Director, Mr Tim Netscher, said the commissioning and ramp-up was progressing well, particularly considering the large-scale complex nature of the Karara Concentrator. “Importantly, all of the major components of the plant – which are the biggest risk area in terms of achieving full plant performance - have operated at up to design capacity,” Mr Netscher said. “The types of minor issues we have dealt with, such as the adjustments required to bring the tailings circuit up to full operating capacity, are well within the parameters of what might normally be expected during the commissioning and ramp-up phase of a major project such as Karara.
“The project team has done a commendable job in quickly identifying and addressing this and other small issues, and we are working towards having the new equipment installed and operating by the end of the Quarter, subject to timely arrival of the required components. We are targeting to achieve full design throughput in July, but if there happen to be any delays I anticipate it will only be measured in weeks.
“The working capital funding issue is a frustrating reality for so many new operations. A great deal has been achieved with the construction and development of this major mining and infrastructure project. We still believe Karara has enormous value and potential. We just need to clear this final hurdle to get to full production levels and we remain committed to assisting KML to source suitable short-term funding options, to try to avoid the need to call on its shareholders again.”
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation















