Century zinc mine life extension project, Australia
Name of the Project
Century zinc mine life extension project.
Location
Queensland, Australia.
Project Owner/s
New Century Resources.
Project Description
An expansion study at the Century zinc mine has highlighted the potential for a mine life extension until mid-2026.
The mine is undertaking a tailings operation that started in August 2018, and is ramping up to its initial Phase 1 design capacity of eight-million tonnes a year. The expansion study considers three scenarios.
Base case – tailings only: This case was developed as part of the 2017 restart feasibility study, initially involving a ramp-up to 15-million tonnes a year of tailings only, with the installation of additional flotation cells and regrind mills. This has been revised to a 12-million-tonne-a-year tailings throughput using only the existing plant.
Case 1 – combination tailings and in situ operation: This involves the openpit mining of two-million tonnes a year, which is a combination of the indicated resources of the South block and East fault block deposits, and processing this run-of-mine concurrently with ten-million tonnes a year of tailings.
Case 2 – combination tailings and in situ: The second option is similar to Case 1, however, with a different in situ blend – 400 000 t/y of Silver King ore through underground mining and 1.6-million tonnes a year of South block/East fault block ore concurrently with ten-million tonnes a year of tailings.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The base case has a net present value (NPV), at an 8% discount rate, of A$879-million.
Case 1 has an NPV of A$1.02-billion and an internal rate of return (IRR) of 46% (incremental on 12-million tonnes a year of tailings).
Case 2 has an NPV of A$1.15-billion and an IRR of 80% (incremental on 12-million tonnes a year of tailings).
Capital Expenditure
Capital expenditure for the base case is estimated at A$40-million.
Case 1 is estimated at A$95-million and Case 2 at A$137-million.
Planned Start/End Date
Under the current schedule, New Century is planning to start its first concentrate production from in situ mining by the second half of the 2021 financial year.
Latest Developments
An in situ feasibility study is under way and will be completed in the third quarter of the 2020 financial year. A decision to mine will be based on the results of this study.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Too early to state.
Contact Details for Project Information
New Century Resources, tel +61 3 9070 3300 or email info@newcenturyresources.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation