PERTH (miningweekly.com) – The development of the Cascavel gold project, in Brazil, was progressing to schedule, with owner Orinoco Gold saying on Thursday that commissioning of the gravity plant was expected to start in March.

Mining of the trail stopes had been scheduled for April and ore from the areas would be batch-treated through the plant to provide information on recovery and reconciliation between the estimated grades and the actual recovered gold.

Processing of large samples ahead of the stoping would provide the most accurate estimates of the actual grades of each stope, the company told shareholders.

Meanwhile, despite heavy rainfall over the wet season, the plant crushing circuit is now fully installed, with the construction of the final stages of the plant completed, and commissioning taking place in March.

The initial commissioning ore would be low-grade ore stockpiled from development headings along with separate parcels of higher-grade material from the initial mining areas.

The high-grade material would be treated by batch, allowing for the development of reconciliation factors between the mine and the mill.

Once in production, Orinoco was hoping to increase production at Cascavel from the planned start-up rate of 40 000 t/y to more than 60 000 t/y by the December quarter.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.048 0.905s - 140pq - 2rq
Subscribe Now