Cairo Solar Farm project, Egypt.

Client
Cairo Solar Farm SAE, a special purpose vehicle comprising Globeleq.

Project Description
The project is part of the first regulatory round of the Egyptian government’s Feed-in Tariff programme, which aims to procure 4 300 MW of renewable-energy capacity.

The Cairo Solar Farm 65 MWp (50 MW ac) solar photovoltaic (PV) development will be located in Egypt’s New and Renewable Energy Agency’s (NREA’s) 37.5 km2 Benban 1.8 GW PV solar park comprising 39 separate PV plots. The project will comprise a single-axis tracking system of about 206 360 PV panels.

Power will be sent to an inverter and fed into the utility power grid system through the Egyptian Electricity Transmission Company (EETC) substation.

The project will be connected to Substation 3 through an underground 22 kV transmission line, which will follow a right-of-way along the route of the internal Benban PV site roads that will be built by the EETC.

Substation 3 will be connected by a high-voltage line to the existing 220 kV high-voltage overhead line about 12 km east of the Benban PV site.

All output generated by the project will be sold to the EETC under a 25-year power purchase agreement.

Value
The project is estimated at $115-million.

Duration
Project procurement and construction will start between the second and third quarters of 2016, and the plant will be operational for a 25-year period, with options to extend the lease after that date.

Latest Developments
Financial close is targeted by the end of 2016.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Globeleq, tel+44 203 823 5500, fax +44 203 761 1900 or email info@globeleq.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Latest News

SKAO director-general Prof Jessica Dempsey
The SKA Observatory has a new head
2nd June 2026 By: Rebecca Campbell

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
Iritron
Iritron

Iritron delivers advanced automation, control, and optimisation solutions to the Mining, Minerals & Metals, Consumer Package Goods and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.057 0.177s - 145pq - 2rq
Subscribe Now