Bunyu graphite project, Tanzania – update

2nd September 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Bunyu graphite project.

Location
Tanzania.

Project Owner/s
Volt Resources.

Project Description
Bunyu has total proven and probable reserves of 2.82-million tonnes grading 6.3% total graphitic carbon. The project will be developed over two stages.

Stage 1 significantly derisks the Stage 2 expansion through a lower-risk, small-scale development.

Stage 1 is premised on a mining and processing plant throughput rate of 400 000 t/y of ore, based on a 6.26% total graphitic carbon feed grade to produce, on average, 23 700 t/y of graphite products over 7.1 years.

Stage 2 will produce about 170 000 t/y over an envisaged 22-year mine life, based on the prefeasibility study that was completed in late 2016 and is used as a proxy for Stage 2.

The DFS for Stage 2 is planned to proceed concurrently with Stage 1 project development.

Potential Job Creation
Stage 1 has a pretax net present value, at a 10% discount rate, of $18.6-million and an internal rate of return of 21%, with a payback after tax of 4.4 years.

Net Present Value/Internal Rate of Return
The Stage 1 feasibility study completed in July 2018 delivers a pretax net present value (NPV), at a 10% discount rate, of $18.6-million and an internal rate of return of 21%, with a payback of 4.4 years.

The Stage 2 prefeasibility study estimates a pretax NPV of $1.31-billion and an IRR of 86.9%, with payback of 1.4 years, based on a 22-year life-of-mine.

Capital Expenditure
Stage 1 has a capital cost of about $31.8-million.

Total initial capital expenditure for the processing plant and all other required infrastructure requirement, such as road upgrades and port warehousing, is estimated at $173-million.

Planned Start/End Date
Not stated.

Latest Developments
Volt Resources has started a feasibility study to update Stage 1 of its Bunyu graphite project.

The graphite producer has said that it will update the processing, infrastructure and logistics for the Stage 1 study, initially released in 2018, and will also update capital and operating cost estimates.

Volt also plans to re-examine other study aspects, including regulatory requirements, marketing and sales, financial analysis and project risks, as well as environmental, social and community requirements.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Volt Resources, tel +61 8 9486 7788 or email info@voltresources.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 
The Steel Tube Export Association of South Africa
Steel Tube Export Association of South Africa

The Steel Tube Export Association of South Africa was established to develop sustainable, internationally competitive carbon steel tube and pipe...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.052 1.141s - 147pq - 2rq
Subscribe Now