Bunyu graphite project, Tanzania
Name of the Project
Bunyu graphite project.
Location
Tanzania.
Client
Volt Resources.
Project Description
Bunyu has total proven and probable reserves of 2.82-million tonnes grading 6.3% total graphitic carbon. The project will be developed over two stages.
Stage 1 is based on a mining and processing facility based on a plant throughput of 400 000 t/y to produce an average 23 700 t/y, with a nominal mine life of 7.1 years.
The proposed mining method is a conventional, drill, blast, load and haul openpit, with waste material stacked in waste dumps. Mining will be undertaken by a contractor under the control and management of Volt Graphite Tanzania personnel and will likely be operated on a 12-hour 365 d/y basis as required.
A bench height of 6 m has been selected, excavated in 3 m × 2 m lifts or flitches. This is considered appropriate for the orebody and the equipment proposed by mining contractors.
Stage 2 will be an expansion of Stage 1 production based on the market demand for Bunyu’s graphite products and leveraging the large-scale graphite mineral resource and Bunyu’s close proximity to critical infrastructure.
Potential Job Creation
Stage 1 has a pretax net present value, at a 10% discount rate, of $18.6-million and an internal rate of return of 21%, with a payback after-tax of 4.4 years.
Value
Stage 1 has a capital cost of about $31.8-million.
Duration
Not stated.
Latest Developments
Volt Resources has been granted two mining licences covering the Stage 1 and Stage 2 developments of its Bunyu graphite project.
The mining licences have been granted subject to three conditions, including an acceptance of the boundaries and coordinates of the amended application, the company accepting the proposed licence, and the payment of $1 000 in preparation fees for each licence.
Volt’s near-term focus remains the successful completion of the proposed $40-million note issue for the Bunyu development.
Following the completion of the note issue, and board approval, Volt will proceed with the front-end engineering and design work for the initial Stage 1 operations, and the ordering of the long-lead time components.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Volt Resources, tel +61 8 9486 7788 or email info@voltresources.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation