Bugoye hydropower plant project, Kasese, Western Uganda.

Project description
The project will require the construction and operation of a 13-MW run-of-river hydropower plant and a six-kilometre-long 33-kV transmission line to connect it to the Ugandan grid.
The plant will located on the Mobuku and Isya rivers in the foothills of the Rwenzori mountains in Kasese district, in western Uganda.

The project will divert water from the two rivers and run it through a five-kilometre-long canal along the contour into a 950-m-long penstock, with a head of 160 m. After passing through two 6,5-MW Francis turbines, the water will be discharged back into the Mobuku river.

Value
The project is expected to cost an estimated $56-million. The International Finance Corporation (IFC) proposes to provide loan finance of $14-million for its own account.

Duration
The plant will take about 21 months to build.

Breakdown of main contracts
Not stated.

Client
Trønder Energi AS (72,5%), and Norfund (27,5%).

Latest developments
None stated.

Participants
IFC (loan finance).

Construction materials
Not stated.

On budget and on time?
Not stated.

Contact details for project information
TrønderEnergi AS vice-president for business development Gunnar Salseggen,
tel +47 73 54 1600, fax +47 73 54 1650
or email gs@tronderenerji.no.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Trotech
Trotech

Design, Construction and Maintenance of Site Erected, Welded Bulk Storage Tanks for the Petrochemical, LNG, Ammonia and Sustainable fuel Sectors.

VISIT SHOWROOM 
Flanders Electrical SA
Flanders Electrical SA

FLANDERS Southern Africa provides integrated solutions for mining and industrial operations, covering field services, automation, electrification,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.057 1.003s - 145pq - 2rq
Subscribe Now