Boorara gold project – Stage 1, Australia – update

24th July 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Boorara gold project – Stage 1.

Location
The project is located 10 km east of Kalgoorlie-Boulder, in the Western Australia goldfields.

Project Owner/s
Horizon Minerals.

Project Description
A feasibility study has indicated a financially viable project.

The proposed mining project comprises predominantly oxide and transitional material contained within the project’s maiden ore reserve.

The Stage 1 openpit operation, which is based on the development of the Regal and Crown Jewel deposits, is expected to produce 159 000 t of ore, producing

9 500 oz of gold over a six-month mine life.

Mining will be conducted using conventional truck-and-shovel operations and will initially be free dig near the surface.

Ore from the openpit operation will be toll-milled at Golden Mile Milling’s one-million-tonne-a-year Lakewood mill, which is located about 7 km from the Boorara operation. The ore will be processed in monthly campaigns under Horizon’s supervision to allow for mill-grade reconciliation data to be compared against the reserve and resource models.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value of A$2.8-million.

Capital Expenditure
The project has low upfront capital costs of A$440 000.

Planned Start/End Date
Not stated.

Latest Developments
The first ore from the Boorara gold mine is being processed by a milling campaign through the Lakewood Mill.

First gold pour is expected shortly and regular milling campaigns are scheduled until January 2021.

Key Contracts and Suppliers
BM Geological Services (geology and resource estimates); Green Geotechnical (geotechnical assessment); Minecomp (mining and ore reserve); ALS Metallurgy and Bureau Veritas Minerals (metallurigical testwork); Rockwater (hydrology and hydrogeology); and Strategen-JBS&G Environmental Consultants (environmental studies).

Contact Details for Project Information
Horizon Minerals, tel +61 8 9386 9534 or email info@horizonminerals.com.au

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.05 1.159s - 127pq - 2rq
Subscribe Now