Blanket development progressing – Caledonia

21st September 2015

By: Megan van Wyngaardt

Creamer Media Contributing Editor Online

  

Font size: - +

JOHANNESBURG (miningweekly.com) – Dual-listed gold miner Caledonia Mining expects to fast-track development and increase production at its Blanket mine, in Zimbabwe, towards the end of the year, owing to having completed a tramming loop ahead of schedule in June.

The company on Monday said it had also completed the sinking of the No 6 Winze, with the shaft currently being equipped as part of the mine’s revised investment plan. This would be followed by horizontal development towards the mine’s two main resource bodies.

The 6 m diameter Central shaft, running from surface to 1 080 m, would provide access to the current inferred mineral resources below 750 m and allow for further exploration, development and mining in these sections along the known Blanket strike, which was about 3 km in length.

Most of the equipment required for the sinking phase was acquired and either on site or in transit to site.

Five generator units with a combined generating capacity of 2 MVA had also been acquired to provide back-up power supply to the kibble winder in the full sink phase, which is expected to start in January. 

The project remained on target for first production in January 2016, with production expected to reach the target rate of 500 t/d in May 2017.

"We are pleased with the ongoing implementation of the revised plan, which is proceeding as scheduled.

"These were significant steps towards progressively increasing production from 2016 onwards to achieve a rate of 80 000 oz/y of gold by 2021. I expect that the shaft’s presink will be completed by the end of the year,” Caledonia CEO Steve Curtis said.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Hanna Instruments (Pty) Ltd
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
Monitor Distributors
Monitor Distributors

We at Hawk High Pressure Pumps specialise in industrial pumps and pumping systems. Our high pressure washing equipment is locally manufactured and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.055 1.111s - 140pq - 2rq
Subscribe Now