Blackwater gold/silver project, Canada – update

27th August 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Blackwater gold/silver project.

Location
British Columbia, Canada.

Project Owner/s
Artemis Gold.

Project Description
Artemis released the results of a prefeasibility study (PFS), based on a revised development approach, in August 2020.

The PFS proposes the staging of the ultimate development of the mine, among other derisking initiatives, which allow for improved economics while enabling the company to phase the development before ramping up to full throughput of 20-million tonnes a year.

The proposed mine plan involves mining 334-million tonnes of ore, 584-million tonnes of waste rock and 83-million tonnes of overburden.  

The project will comprise the construction, operation and closure of an openpit gold and silver mine and ore-processing facilities, starting with a nominal milling rate of 15 000 t/d, or 5.5-million tonnes a year.  

The ore-processing facilities will be expanded to achieve 33 000 t/d, or 12-million tonnes a year, starting in Year 6, with a final expansion to achieve 55 000 t/d, or 20-million tonnes a year, starting in Year 11.  

The material will be sourced through conventional openpit mining methods, initially targeting high-grade, near-surface ore for processing, with lower-grade material being stockpiled for processing at the end of the mine life.

Most of the waste material sourced from the pit will be used to build the tailings storage facility (TSF) or placed in the TSF. Overburden and nonpotentially acid-generating waste-rock not required for construction will be placed in stockpiles adjacent to the openpit. Potentially acid-generating waste-rock, along with tailings, will be deposited into the TSF located to the north-northwest of the openpit.

In addition to the site infrastructure, a proposed 134 km, 230 kV transmission line will be built from the BC Hydro Glenannan substation near Endako, in British Columbia, to provide power for the project.

Openpit mining methods, comprising drill, blast, load and haul, will be used. 

The openpit mine is expected to operate for 18 years, excluding 15 to 18 months of preproduction mining. Following mining operations, stockpiled low-grade material will be processed for an additional five years, resulting in a total life-of-mine of 23 years.  

The openpit will be developed with a series of pushbacks. The first stage will target suitable waste rock for construction while exposing near-surface, high-grade material. The second phase will target higher-grade, lower-strip-ratio ore, providing mill feed over the initial years of the project.  The remaining stages expand the pit to the north, targeting progressively deeper ore.

The mining and fleet maintenance operations will be owner-managed. The mine equipment fleet is planned to be bought through lease arrangements.

Potential Job Creation
An economic-impact study completed by KPMG on the Blackwater project in November 2020 anticipates the project will create 457 direct full-time jobs a year over the 23-year operating life of the mine, with 825 direct full-time jobs a year created during the construction and/or expansion phases of mine development.

Net Present Value/Internal Rate of Return
The base case estimates an after-tax net present value, at a 5% discount rate, of $2.25-billion and an internal rate of return of 34.8%, with a payback on initial capital of two years.

Capital Expenditure
The base case estimates an initial capital cost of $592-million.

The Phase 2 expansion will cost about $426-million and Phase 3 $398-million.

Planned Start/End Date
Not stated.

Latest Developments
Artemis Gold has made the final payment of C$50-million to New Gold for the acquisition of the Blackwater gold project.

In July 2021, British Columbia approved early construction works – the first step required for mine construction – at the Blackwater project. The permit allows for the necessary site preparation and land clearing work to begin. 

Key Contracts, Suppliers and Consultants
Moose Mountain Technical Services, with support from Knight Piésold (PFS).

Contact Details for Project Information
Artemis Gold, tel +1 604 558 1107 or email info@artemisgoldinc.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 
The Steel Tube Export Association of South Africa
Steel Tube Export Association of South Africa

The Steel Tube Export Association of South Africa was established to develop sustainable, internationally competitive carbon steel tube and pipe...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.07 1.019s - 147pq - 2rq
Subscribe Now