https://www.engineeringnews.co.za

Beyondie sulphate of potash project, Australia

1st February 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Beyondie sulphate of potash project (BSoPP).

Location
Western Australia.

Client
Kalium Lakes Limited (KLL).

Project Description
A definitive feasibility study (DFS) on the BSoPP has demonstrated that the project is economically and technically robust and has the potential to generate substantial value for shareholders.

Based solely on the Stage 1 approval footprint, which represents less than a quarter of the total lake surface area within the tenement package, the project has a proven reserve of 1.65-million tonnes, grading 13830 mg/ℓ SoP at a cutoff grade of 2 500 mg/ℓ potassium and a probable reserve of 3.49-million tonnes grading 11 820 mg/ℓ SoP at a cutoff grade of 2 500 mg/ℓ potassium.

The DFS proposes the development of a subsurface brine deposit to initially produce 82 000 t/y of SoP before expanding to produce 164 000 oz/y of SoP product through evaporation and processing within the Stage 1 Beyondie, 10 Mile and Lake Sunshine tenement holdings. Further expansion into the eastern tenement area – Stage 2 – could result in future expansion of up to 250 000 t/y of SoP. BSoPP has a mine life of 30 years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of A$575-million and an internal rate of return of 20.4%, with an initial payback of seven years.

Value
Preproduction capital for Stage 1 is estimated at A$159.6-million. A deferred capital cost of A$125.3-million is required to ramp up the project to 164 000 oz/y.

Duration
Production is expected in 2020.

Latest Developments
KLL has received environmental approval for its BSoPP.

The environmental approval covers the Stage 1 area of the project, which is based on the base case production of 164 000 t/y of SoP over a mine life of 30 years.

Key Contracts and Suppliers
KLL (DFS), K-UTEC, DRA Global, Advisian, Shawmac, Wyntak and Preston Consulting (principal technical consultants); RSM, DLA Piper Australia, HopgoodGanim Lawyers and BurnVoir Corporate Finance (accounting, legal, commercial and financial advisers).

On Budget and on Time?
Not stated.

Contact Details for Project Information
KLL, tel +61 8 9240 3200 or email info@kaliumlakes.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.081 1.145s - 147pq - 2rq
Subscribe Now