Bepkong underground gold project, Ghana

6th September 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

This article has been supplied.

Name of the Project
Bepkong underground gold project.

Location
Ghana.

Project Owner/s
Azumah Resources and joint venture partner Ibaera Capital.

Project Description
A scoping study on the Bepkong project has indicated that an underground mining operation could provide a material boost to Azumah’s already financially robust openpit-based Wa gold project.

The study proposes a production target of an additional 154 000 oz of contained gold.

Mineralisation is proposed to be accessed by a portal and ramp, starting 40 m above the base of the currently planned Bepkong openpit and will continue to a depth of 450 m below surface.

Conventional open stoping is the preferred mining method, with ore and waste being trucked to surface.

The preliminary mining schedule will be for an estimated initial 4.5 years at an average mill feed grade of 3.21 g/t gold.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project is expected to have a pretax net present value, at a 5% discount rate, of $177-million and an internal rate of return of 35%, with a payback of 1.6 years.

Capital Expenditure
Provisional capital costs will comprise about $36-million for development and diamond drilling, $78-million for underground mining costs and $29-million for processing costs.

Planned Start/End Date
Systematic development and mining operations could start towards the end of the openpit development at Bepkong, which is currently scheduled for Year 2 in the feasibility study schedule.

Latest Developments
The JV has not made a production decision and its strategic plan to develop a gold mining operation is subject to the results of a feasibility study on the Wa gold project and other factors.

Key Contracts and Suppliers
Orelogy Mine Consulting (scoping study).

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Azumah Resources, tel +61 8 9486 7911 or email info@azumahresources.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.059 1.155s - 146pq - 2rq
Subscribe Now