Name of the Project
Barossa project to backfill Darwin liquefied natural gas (DLNG) plant.

Location
The project is located 300 km north of Darwin, within Santos’ Northern Australia portfolio, one of the company’s core long-life, natural gas assets.

The project area encompasses petroleum permit NT/RL5 over the Barossa field and petroleum permit NT/RL6 to the south over the Caldita field to be developed as a potential future phase of the project.

Client
Santos holds a 25% interest in the Barossa Caldita joint venture (JV), along with operator ConocoPhillips (37.5%) and SK E&S (37.5%).

Project Description
The Barossa development comprises a floating production storage and offloading facility, with six subsea production wells to be drilled in the initial phase, supporting in-field subsea infrastructure and a gas export pipeline tied into the existing pipeline between Bayu-Undan and Darwin. T

The project aims to provide gas for DLNG after the Bayu-Undan reservoir ceases production post 2022.

Barossa’s development will extend the operating life of DLNG by more than 20 years.

Potential Job Creation
Not stated.

Value
Not stated.

Duration
Not stated.

Latest Developments
The Barossa Caldita JV announced in April that the Barossa project would enter the front-end engineering and design (FEED) phase for the development of the Barossa project to backfill the Darwin LNG.

FEED activities will involve engineering and commercial work aimed at finalisation of the project’s technical detail, costs, LNG sales agreements and negotiation of access arrangements with the owners of DLNG and the Bayu-Undan to Darwin gas pipeline.

A final investment decision is targeted towards the end of 2019.

Contracts for field surveys and engineering for the FPSO, subsea facilities and export pipeline will be awarded shortly.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Santos media enquiries Joanna Vaughan, tel +61 2 9276 1134 or email joanna.vaughan@santos.com; or investor enquiries Andrew Nairn, tel +61 8 8116 5314 or email andrew.nairn@santos.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

The Steel Tube Export Association of South Africa
Steel Tube Export Association of South Africa

The Steel Tube Export Association of South Africa was established to develop sustainable, internationally competitive carbon steel tube and pipe...

VISIT SHOWROOM 
Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.061 1.19s - 145pq - 2rq
Subscribe Now