Barberton tailings retreatment project, South Africa
This article has been supplied.
Name and Location
Barberton tailings retreatment project (BTRP), Mpumalanga, South Africa.
Client
Pan African Resources (PAR).
Project Description
Situated adjacent to the Bramber tailings storage facility (TSF) at the Fairview mine, the project is designed to retreat 100 000 t/m of gold tailings at an estimated average cash cost of $800/oz.
The plant uses a carbon-in-leach process, followed by electrowinning and smelting to produce a saleable gold product.
The project will source about 12 000 t/m of current tailings through a pipeline from the Fairview concentrator and BIOX plant, as well as an estimated 88 000 t/m from the Bramber TSF.
The project has a current life of mine of six years and will provide Pan African with an additional 20 000 oz/y of gold.
Value
The total capital expenditure budget of the project was R305-million, of which about 90% has been invoiced to date. All of the construction capital requirements were funded through internal cash flows from Barbertons Mines.
Duration
The BTRP project, which started construction in April 2012, was successfully commissioned on June 28, 2013.
Latest Developments
The BTRP undertook its inaugural gold pour on June 28 and is expected to ramp up to full capacity of 100 000 t/m at an average recovered grade of 0.52 g/t by the second quarter of 2014.
The BTRP has created an additional 86 direct employment opportunities in the Barberton area.
Key Contracts and Suppliers
Basil Read-Matomo (feasibility study, design, procurement and construction).
On Budget and on Time?
The BTRP project was completed on schedule and within budget.
Contact Details for Project Information
PAR, Elizma Coetzee, tel + 27 11 243 2900, fax + 27 11 880 1240 or email ecoetzee@paf.co.za.
Basil Read, tel +27 11 418 6300 or fax +27 11 418 6333.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation