Barberton Mines complex head grade rises 32% – Pan African

ELIKHULU PROCESS PLANT Construction on the Elikhulu tailings retreatment project is progressing ahead of schedule with first gold expected in August
JOHANNESBURG (miningweekly.com) – The average head grade of Pan African Resources’ Barberton Mines complex, which includes the Fairview, Sheba and Consort mines, has increased by 32%.
The head grade improved from an average of 8.7 g/t during July to December 2017 to 11.5 g/t last month, predominantly as a result of mining high-grade ore at the 272 platform since January.
The latest on-reef development samples taken in the 272 platform recorded an average grade of 99.2 g/t (ranging from 2.2 g/t to 1 320 g/t) over a mineralised width of 3.36 m along a strike length of 24 m.
This confirms that the high-grade areas of this mining block are now in production, Pan African said on Friday.
Further, face sampling of the on-reef development, taken of the mineralised 11 block MRC orebody at the 358 platform, resulted in an average grade of 45.7 g/t over a mineralised width of 2 m, confirming that the on-reef development has reached the high-grade section of this mining block.
Meanwhile, construction on the Elikhulu tailings retreatment project is progressing ahead of schedule with first gold expected in August. Ramp-up to full production of about 55 000 oz/y is expected to take no longer than two months, after which Elikhulu is estimated to produce gold at an all-in sustaining cost of production of below $650/oz, at the prevailing rand/dollar exchange rate.
Together with the Evander Tailings Retreatment Plant, Elikhulu is expected to produce more than 70 000 oz/y of gold.
Additionally, the construction of the Barberton Tailings Retreatment Plant’s (BTRP’s) regrind mill is proceeding according to schedule with commissioning anticipated in the last week of April. On commissioning of the regrind mill, production at the BTRP is expected to increase to about 21 000 oz/y.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation