https://www.engineeringnews.co.za

B2Gold completes Fekola mill expansion ahead of schedule

11th September 2020

By: Creamer Media Reporter

     

Font size: - +

Canada-based B2Gold has successfully expanded the mill at the Fekola mine, in Mali, to 7.5-million tonnes a year, about one month ahead of the scheduled completion date of September 30.

Four days after startup, a five-day mill performance test was conducted from August 26 to August 30. The results of the performance test exceeded design in throughput, gold recovery, grind and availability over the five-day period.

The minor, outstanding construction work is expected to be completed by mid-September.

B2Gold says the Fekola mine continues to operate unimpeded and no operational days have been lost owing to the recent political developments in Mali, or the Covid-19 pandemic.

The company has maintained its consolidated production guidance at between 1-million and 1.05-million ounces of gold, while total consolidated cash operating costs are forecast to be between $415/oz and $455/oz and total consolidated all-in sustaining costs are forecast to be between $780/oz and $820/oz. 

Edited by Mariaan Webb
Creamer Media Contract Publishing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Monitor Distributors
Monitor Distributors

We at Hawk High Pressure Pumps specialise in industrial pumps and pumping systems. Our high pressure washing equipment is locally manufactured and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.072 1.001s - 140pq - 2rq
Subscribe Now