Name of the Project
Arcadia lithium project.

Location
Outside Harare, in Zimbabwe.

Project Owner/s
Prospect Resources (87%).

Project Description
An updated definitive feasibility study (DFS) on Arcadia, released in December 2019, confirmed the project’s strong financial and geological merits, positioning the company to be a leading producer of lithium and battery minerals.

The project’s total proven and probable reserves have increased from 26.9-million tonnes grading 1.31% lithium oxide and 128 parts per million (ppm) tantalum pentoxide in the 2018 DFS to 37.4-million tonnes grading 1.22% lithium oxide and 121 ppm tantalum pentoxide in the updated 2019 DFS.

The updated DFS envisages a 2.4-million-tonne-a-year conventional openpit mining operation, producing average concentrate of about 173 000 t/y of 6% spodumene, 24 000 t/y of chemical grade petalite and 98 000 t/y technical grade petalite at a concentrate grade of 4%, as well as 174 000 lb/y of tantalum at a concentrate grade of 25%. Mineral processing will be based on using conventional beneficiation techniques, including the gravity-based processes of dense-medium separation and spirals, to recover petalite and tantalite. Froth flotation will be used to recover spodumene.

Process tailings will be disposed of to an engineered tailings storage facility.

The project’s mine life has been extended from 12 years to 15.5 years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project’s pretax net present value has increased from $511-million, at a 10% discount rate in the 2018 DFS, to $710-million in the updated 2019 DFS.

The pretax internal rate of return has increased from 44% in the 2018 DFS, with a payback of 2.5 years, to 71%, with a payback of 18 months in the updated 2019 DFS.

Capital Expenditure
The preproduction capital cost of the project has decreased from $165.2-million in the 2018 DFS to $162.4-million in the updated 2019 DFS.

Planned Start/End Date
The ground-breaking ceremony for the project was held in November 2018.

The project is expected to be completed in the third quarter of 2020, with commissioning from November 2020.

Latest Developments
Prospect Resources will raise A$6-million through a share placement to institutional investors to advance the development of its Arcadia lithium project.

Prospect has received subscriptions for more than 46.1-million shares at 13c each in a private placement to sophisticated and professional investors.

The funds raised from the placement will go towards the production of samples for downstream offtakers and customers through the design, supply and operation of a flotation pilot plant to undertake front-end engineering design for the Arcadia project, and to fund project finance activities and working capital.

Key Contracts, Suppliers and Consultants
Roger Tyler (resource definition); ADP Marine & Modular (DFS – process design review, final engineering cost estimate, health, safety and environment management plan, project execution plan and quality management plan); DRA Global (process design); Gayle Hanssen (resource modelling); Adam Moodley (project geologist); Practara (geotechnical services); David Miller (mine planning and minerals marketing); Envirosmart (environmental-impact assessment); Constant Chuma (hydrogeological assess­ment); Mike Kitney (metallurgy); Blonton Management (tailings disposal facility design); Norconsult (electrical network analysis); JJ Transport (transport fleet study); Lee John (consultant metallurgist); Trevor Barnard (project manager); and Iain Sheasby (project modelling).

Contact Details for Project Information
Prospect Resources, tel +61 8 9217 3300 or email info@prospectresources.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.052 0.764s - 147pq - 2rq
Subscribe Now