Ancuabe costs lower as output increased

11th July 2023

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – An updated definitive feasibility study (DFS) into the Ancuabe graphite project, in Mozambique, has resulted in a decrease in up-front capital expenditure (capex) and an increase in expected yearly production.

ASX-listed Triton Minerals on Tuesday said that the updated DFS had reduced the up-front capex from the $99.1-million previously estimated, to $90.3-million, while increasing processing plant throughput from 1-million tonnes a year to 1.2-million tonnes a year, resulting in graphite production increasing from 60 000 t/y to 70 000 t/y.

Triton last year re-committed itself to the full-scale development of the Ancuabe project, as envisioned in the original 2017 DFS, which estimated a mine life of 27 years.

The decision to pursue a large-scale development came after Triton completed a strategic review and desktop study in 2022 considering various alternatives to bring the Ancuabe project into production in the short term, including a Stage 1 development of a commercial pilot plant producing 5 000 t/y to 8 000 t/y of graphite concentrate, which would later be expanded to the Stage 2 project targeting the 60 000 t/y production.

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Rosond
Rosond

ROSOND provides fast, efficient, safe, and cost-effective drilling and grouting services to mining and exploration industries throughout Africa.

VISIT SHOWROOM 
AirNox Pty Ltd
AirNox Pty Ltd

AirNox (Pty) Ltd is a level 1 BBBEE manufacturer of complete AdBlue® solutions for operators of SCR diesel engines and AUS40 across South Africa...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.065 1.265s - 140pq - 2rq
Subscribe Now