https://www.engineeringnews.co.za

Agbaja iron-ore project, Nigeria

6th May 2016

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Agbaja iron-ore project, Kogi state, Nigeria.

Client
Kogi Iron.

Project Description
The Agbaja plateau hosts an extensive, shallow, flat-lying channel iron deposit and mineral resources currently estimated at 586-million tonnes at 41.3% iron (within EL12124). Most of the mineral resources are classified as indicated (466-million tonnes at 41.4% iron) and the balance as inferred (120-million tonnes at 41.1% iron).

The Agbaja mineral resource was the basis for the project’s prefeasibility study (PFS). There are sufficient indicated mineral resources at Agbaja to support a five-million-tonne-a-year iron-ore mining and processing operation for more than 35 years. A mine plan sufficient for 21 years of production was used in the PFS.

The PFS completed in January 2014, proposes the construction of the mine in two stages. The estimated 7.2 km2 Stage 1 mining area, west of the plant site, contains about 158-million tonnes of indicated mineral resources. Targeting the magnetic fraction of the indicated mineral resource, the average grade of material identified for mining is estimated at 46.1% iron, with a corresponding strip ratio of about 0.55:1. As currently designed, this area will provide processing plant feed for an initial 15 years at the planned concentrate production rate of five-million tonnes a year.

The estimated 2.2 km2 Stage 2 mining area is situated to the east of the plant site and contains about 66-million tonnes of the indicated mineral resources. The average grade of material is estimated at 44.8% iron, with a strip ratio of about 0.56:1. This area will provide processing plant feed for an additional six years, bringing the combined plant feed from the two areas to 21 years at a concentrate production rate of five-million tonnes a year. Kogi has opted for a mining contractor to conduct all site development, overburden and waste removal, as well as openpit mining, including site rehabilitation, haulage and ore feed to a primary crusher. Mining operations will be conducted 24/7, 365 days a year and it is envisaged that production drilling and blasting will not be required, as all material is regarded as soft, friable and amenable to “free-dig”.

The processing plant will have a primary grind size of 600 μm, with a final grind size at a relatively coarse 250 μm.

Grinding will be followed by low-intensity magnetic separation (LIMS). This technology has demonstrated reliable primary separation of iron-bearing material for a reasonable final product grade and yield after regrinding of the material. Yield is estimated at 45% for a final iron-ore concentrate grade of about 56% iron.

The concentrate slurry will be filtered at Banda to have a moisture content of less than 10% and BE conveyed to a covered stockpile. Barge loading will be by a travelling, luffing, telescoping barge loader filling Mississippi-type barges, in a configuration of four barges. The iron-ore concentrate will be transported an estimated 602 km from Banda along the Niger river to the Escravos Transfer Station in the Niger Delta.

At the Escravos transfer station, the concentrate will be transferred into a 20 000 t self-propelled and self-unloading ocean barge.

Net Present Value/Internal Rate of Return
The project has an estimated pretax net present value, at a 12% discount rate, of $420 million and an internal rate of return of 23.7%, with a four-year capital payback.

Value
Capital costs are estimated at $497.1-million.

Duration
First production is expected between the end of the fourth quarter of 2016 and the first quarter of 2017.

Latest Developments
Kogi is advancing its Agbaja project towards development following successful tests conducted to determine the smelting characteristics of the project’s ore.

Kogi is hoping to build an initial mining operation alongside a 250 000 t/y steel product processing plant at Agbaja. The long-term plan is for a major-scale operation of about five-million tonnes a year.

The plant is expected to have the ability to produce three products, with the possibility of quickly switching between the various product runs, depending on customer demand.

The project is estimated to require a capital spend of about $200-million, with the majority of the capital to be spent on infrastructure and the processing plant.

Kogi has indicated that with the completion of metallurgical testing, the company was moving to finalise a definitive feasibility study on the Agbaja project, which is expected to be complete by the end of June.

Meanwhile, offtake negotiations for the Agbaja product have mostly been centred around steelmakers in Nigeria and Europe.

The company has also stated its intentions to renew negotiations with prospective funding partners for the Agbaja project within the coming weeks, as project funding would likely be raised at company and project level.

Kogi currently holds approvals to explore the Agbaja tenements and is progressing to transition to a mining permit. The company will also amend its environmental-impact statement to reflect the change in scope from the originally planned direct shipping ore mining operation to an integrated mining and sell products project.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Kogi Iron, tel +61 8 9200 3456, fax +61 8 9200 3455 or email info@kogiiron.com.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Roytec Global (Pty) Ltd
Roytec Global (Pty) Ltd

Roytec Global is an international company specializing in liquid / solid and mineral separation technologies for the Mining and Industrial sectors.

VISIT SHOWROOM 
Virtual Gas Network (Pty) Ltd
Virtual Gas Network (Pty) Ltd

Virtual Gas Network supplies compressed natural gas via a virtual gas distribution network.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 1.093s - 148pq - 2rq
Subscribe Now