Abu Qir steam power project, Egypt.

Project description
The project involves the design, fabrication, delivery, installation and commissioning of two complete steam turbine-generator sets, with a nominal capacity of 650 MW each, including auxiliaries. The output of each generator will be connected to 21/500-kV generator transformers.

Five 500-kV bays of indoor gas-insulated switchyard will be designed, supplied and installed to connect the generator transformers and the switchyard. This will also include installation of protection, communication and control systems in the switchyard building.

The civil works for the project will comprise the construction of access roads, site preparation, piling and foundation works, buildings, structural steel, underground piping, the construction of cooling water intake and discharge structures, and the construction of a portable water system and a sewerage system. The objective of the project is to increase the generation capacity of the unified power system by about 4% in 2012, to meet the electricity demand on the system in the short to medium term.

Value
The project is estimated to cost $1,3-billion. The African Development Bank (AfDB) has approved a loan of $325-million for the project.

Duration
The project will be implemented over 53 months from July 2007. Completion is scheduled for November 2011.

Breakdown of main contracts
Not stated.

Client
Egyptian Electricity Holding Company (EEHC) and West Delta Electricity Production Company (WDPC).

Latest developments
A project implementation team has been established to closely supervise the implementation of the project. The WDPC/EEHC has appointed a consulting firm to assist in the preparation of a detailed engineering design and the tender documents, and construction supervision, including monitoring the implementation of the environmental and social management plan.  

Participants
AfDB (loan finance) and EEHC/WDPC (project implementation supervision and bank liaison).

Construction materials
Not stated.

On budget and on time?
Not stated.

Contact details for project information
EEHC, tel +20 2 403 0681 or
fax +20 2 402 9828.
AfDB, Felix Njoku, tel +216 71 10 26 12 or
email f.njoku@afdb.org.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 
The Steel Tube Export Association of South Africa
Steel Tube Export Association of South Africa

The Steel Tube Export Association of South Africa was established to develop sustainable, internationally competitive carbon steel tube and pipe...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.053 0.788s - 145pq - 2rq
Subscribe Now