Vaal Gamagara water supply scheme – Phase 2, South Africa – update

Image of water drop

1st May 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name and Location
Vaal Gamagara water supply scheme (VGWSS) – Phase 2.

Location
Gamagara, Northern Cape, South Africa.

Project Owner/s
Vaal Gamagara Water User Association.

Project Description
The Phase 2 project is the long term solution to ensure sustainable water security for mining and regional users. The core function of the scheme is the distribution of purified bulk water for mining, industrial and domestic use, and will provide a sustainable water supply until 2040.

The project includes the upgrade of the water scheme, which comprises a raw water pumpstation, purification works, six booster pumpstations, several reservoir facilities and a pipeline network of about 470 km from the Vaal to Hotazel.

Capital Expenditure
The estimated cost is R18-billion.

Planned Start/End Date
The project is scheduled for completion by June 2027.

Latest Developments
The project has progressed to the engineering and design stage. 

Consulting engineers appointed by the Vaal Gamagara Water User Association have started specialist studies and detailed engineering design. 

Preliminary work on the funding model and market sounding is also nearing completion. 

Over the next 18 months, the project team will continue developing the Phase 2 programme, in line with the governance and funding framework being established between the Department of Water and Sanitation, and the commercial users.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Gamagara Local Municipality, tel +27 53 723 6000.
DWS director: media liaison Wisane Mavasa, tel  +27 12 336 8264 or email mavasaw@dws.gov.za.


 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Environmental Impact Management Services
Environmental Impact Management Services

EIMS is an independent specialised environmental consulting firm offering the full spectrum of environmental management services across all sectors...

VISIT SHOWROOM 
Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.09 0.908s - 157pq - 2rq
Subscribe Now