Thor Wind Farm, Denmark – update

Photo by RWE
Name of the Project
Thor Wind Farm.
Location
Danish North Sea, about 22 km from Thorsminde, on the west coast of Jutland.
Project Owner/s
RWE (51%) and Norges Bank Investment Management (49%). RWE is responsible for construction and operations throughout the project’s life cycle.
Project Description
RWE plans to build Denmark’s biggest offshore wind power plant to date, with the capacity to produce enough green electricity to supply the equivalent of more than one-million Danish households.
The 1 100 MW wind farm will comprise 72 offshore wind turbines, each with a capacity of 15 MW and a 236-m-diameter rotor with a swept area of 43 500 m².
Potential Job Creation
The project is expected to create up to 60 permanent jobs.
Capital Expenditure
Not stated.
Planned Start/End Date
Testing and full commissioning are scheduled for completion by spring 2027, with full commercial operation planned for 2027.
Latest Developments
RWE had installed 36 of the project’s 72 turbines by July 17, 2026, marking the halfway point in the offshore turbine-installation campaign.
Installation is being undertaken from the Port of Esbjerg using Fred Olsen Windcarrier’s Brave Tern installation vessel.
Thor will be the first offshore wind farm to use 36 carbon-reduced steel turbine towers from Siemens Gamesa. Forty turbines will also be fitted with 120 recyclable rotor blades.
Key Contracts, Suppliers and Consultants
Siemens Gamesa (wind turbines); Fugro (geotechnical site investigation); and Fred. Olsen Windcarrier (turbine installation using the Brave Tern vessel).
Contact Details for Project Information
RWE Offshore Wind, tel +49 201 5179-5008 or email communications@rwe.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation