https://www.engineeringnews.co.za
Africa|Construction|Consulting|Consulting Engineers|Contractor|Cutting|Design|Engineering|PROJECT|Projects|Resources|Road|Roads|Service|Services|transport|Infrastructure
Africa|Construction|Consulting|Consulting Engineers|Contractor|Cutting|Design|Engineering|PROJECT|Projects|Resources|Road|Roads|Service|Services|transport|Infrastructure
africa|construction|consulting-company|consulting-engineers|contractor|cutting|design|engineering|project|projects|resources|road|roads|service|services|transport|infrastructure

Cancelled Sanral contracts to be readvertised, awards expected by end of September

3rd June 2022

By: Irma Venter

Creamer Media Senior Deputy Editor

     

Font size: - +

The board of the South African National Roads Agency Limited (Sanral) has instructed Sanral management to readvertise and award the R17.47-billion in tenders the board cancelled last month, citing “material irregularities”, within the next four months,

Speaking at a media conference in Centurion last week, Sanral board chairperson Themba Mhambi added that the board would recruit an independent public institution with infrastructure expertise to assist with the process to advertise and adjudicate the tenders, and to make a recommendation to the board on the winning bidders.

This body has been identified, he noted, but not yet employed.

“This process has been soiled and its integrity has been compromised internally within Sanral,” said Mhambi. “We are clear as a board that prima facie evidence exists of people speaking to the very bidders from inside Sanral, based on the media articles we are seeing.”

The tenders which the Sanral board did not approve are for the Mtentu Bridge Wild Coast project, on the N2, valued at R3.4-billion; the rehabilitation of the R56 Matatiele, in the Eastern Cape, valued at R1-billion; the N3 Ashburton interchange, in KwaZulu-Natal, valued at R1.8-billion; and improvements to the EB Cloete interchange (N2 and N3 connection point in KwaZulu-Natal), valued at R4.3-billion.

The Open Road Tolling tender in Gauteng, valued at R6.88-billion, lapsed and was not renewed.

Sanral noted in an earlier statement that the tenders were cancelled due to “a material irregularity in the tender process”, where a resolution made by its board in January 2020 was not implemented in the evaluation of the affected tenders.

Transport Minister Fikile Mbalula said that he was awaiting a report from the board on the matter. He emphasised that it was important not to repeat the mistakes made during the State capture era, or to allow malfeasance for the sake of expediency.

Mbalula advised those aggrieved by the cancellation to challenge the decision in court.

2020 Board Resolution Mhambi explained that all the five cancelled tenders had one thing in common – the absence of the implementation of a resolution of the Sanral board regarding the separation of duties.

He said the board discovered in January 2020 that the construction contractor bid evaluation process within Sanral had a “major and potentially corruptive flaw”.

He said the process allowed the same service provider which developed the design drawings and technical specifications for projects (which are then advertised) to also be the party to determine, on a technical level, which bid would be recommended for award to the bid evaluation committee.

“Now, if that is not a conflict of interest, if that does not have the potential to promote corruption, someone must tell me we are crazy as a board,” said Mhambi.

“In 2020, we said that the consultants involved in the drawing up of specifications should not be involved in the evaluation of the technical submissions by bidders. Let another independent engineering consultant look at the bids and make a recommendation.

“Then we discovered that our recommendation has not been effected, and we sanctioned the award of these tenders . . . as violating an internal control.

“Contrary to the board’s instructions in all the tenders at issue, the design of the project and the development of the technical specifications was the same individual or entity which decided on the technical bids to be considered for award.

“One person doing all these things is extremely dangerous, as it effectively makes one service provider almost the sole determiner [of] who gets Sanral contracts. It flies in the face of a fair, equitable, cost-efficient and transparent procurement process,” said Mhambi.

“No one could guarantee that no collusion took place.”

Other Lapses
While all five contracts were found wanting with regard to the 2020 resolution, other lapses were also discovered in the Mtentu, Ashburton projects, as well as the Open Road Tolling project.

Concerning

the process to build the Mtentu bridge, a bid that should have been disqualified because it was not submitted in the prescribed format in terms of the specifications was accepted.

This should not have been the case, said Mhambi.

The specifications also allowed for a flawed increase in the scope of work in order to accommodate the 30% subcontracting demand requirement, which effectively drew a line through this requirement.

“This deviation was done without the requisite board approval and was, therefore, irregular,” said Mhambi.

Yet another flaw was that one specific bidder was allowed to provide guarantees –“and not even secured – instead of implementing the principle of Sanral retaining money owed as “insurance against shoddy work, or work not being completed”, said Mhambi.

“All bidders have to be treated in the same way.”

Within the Ashburton tender, it was discovered that a bidder which was not supposed to be disqualified was indeed disqualified.

And, lastly, with regard to the Open Road Tolling project, the 30% subcontracting requirement was dropped to 15%.

Within government, companies awarded large contracts must subcontract 30% of the contract value, with the emphasis on providing work to smaller companies and/or communities.

Consequences
The Sanral board is as concerned as anyone in the industry about the effects the cancellation of the tenders will have on the implementation of critical infrastructure projects in South Africa, as well as on the construction industry, said Mhambi.

“However, it cannot be said that the governance and procurement processes must be compromised at all and any costs.

The State-owned entity (SOE) sector is still reeling from the consequences of cutting corners. Short memories in this regard are unfortunate.”

Mhambi added that the board was “determined” to get to the bottom of the lapses and irregularities, and to follow up with the relevant consequence management.

He also noted that the procurement processes within Sanral only allowed for board scrutiny of projects above R750-million, and that the agency would have to investigate any lapses in tender awards below this threshold.

Decision Challenged
Consulting Engineers South Africa (Cesa) issued a statement last week saying it disagreed with the Sanral board’s decision to cancel “critical infrastructure tenders” on the basis of the involvement of design engineers.

“There is a clear lack of understanding of the role of an independently appointed design engineer in the contractor tender adjudication process,” noted Cesa CEO Chris Campbell.

“A consulting engineer can be involved first in the design of an infrastructure project, followed by tender adjudication analysis and then possibly site supervision services – all acting as the trusted adviser to the client body, especially when a public-sector client has limited specific experienced resources.

“Failing to address such capacity challenges within the public sector in this manner will have significant consequences on our ability to leverage infrastructure development as a catalyst for our economic recovery,” said Campbell.

“The role of a design engineer is to provide independent advice to the client body, acting as the owner’s engineer,” he added.

“The design or consulting engineer is distinctly separate from the contractor and is bound by a code of ethics and has a huge risk exposure in performing this duty.

“In fact, an engineer in this position found to be acting unethically could put his company at risk of being expelled from Cesa and the individual responsible could be disbarred from providing such professional services by the Engineering Council of South Africa.”

The appointment of the consulting engineer, as the trusted adviser to the client, is distinct from that of the contractor, so there is no conflict of interest as alleged by the current Sanral board, stated Campbell.

“In many instances, Sanral is not unique; many other public entities and SOEs have been adopting a similar approach and continue to do so, all with the same governance considerations and accountability, none of whom have been found wanting in this respect by the Office of the Auditor-General.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Goodwin Submersible Pumps Africa (Pty) Ltd
Goodwin Submersible Pumps Africa (Pty) Ltd

Goodwin Submersible Pumps Africa is sole distributors for Goodwin electrically driven, submersible, abrasion resistance slurry pumps.

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.082 0.132s - 161pq - 2rq
Subscribe Now