Koruson 2, South Africa – update

Photo by EDF
Name of the Project
Koruson 2.
Location
On the border of the Northern and Eastern Cape provinces of South Africa.
Project Owner/s
Envusa Energy, a joint venture between Anglo American and EDF power solutions.
Project Description
Envusa Energy completed the project financing for its first three wind and solar projects, collectively known as Koruson 2, in February 2024.
The renewable-energy projects will have a total capacity of 520 MW of wind and solar electricity generation, and will comprise the Umsobomvu Wind Farm (140 MW), the Hartebeesthoek Wind Farm (140 MW) and the Mooi Plaats solar project (240 MW).
When fully operational, the Koruson 2 cluster is expected to abate about 2.2-million tonnes a year of CO2.
The power supplied by the cluster is intended to displace coal-based grid electricity at Anglo American’s platinum, iron-ore and diamond operations in South Africa. Anglo American Platinum has contracted 461 MW, Kolomela mine 11 MW and Venetia mine 48 MW under 20-year offtake agreements with Envusa Energy.
Potential Job Creation
The construction phase generated thousands of direct and indirect jobs across the Eastern Cape and Northern Cape. Envusa has also committed R20-million to socioeconomic development for the Inxuba Yethemba and Umsobomvu communities.
Capital Expenditure
Not stated.
Planned Start/End Date
The Mooi Plaats solar PV facility and the Umsobomvu Wind Farm reached commercial operation by April 2026. As at April 9, 2026, Hartebeesthoek remained on track to reach commercial operation in June 2026, completing the 520 MW cluster.
Latest Developments
Envusa’s 140 MW Umsobomvu Wind Farm reached commercial operation shortly after the 240 MW Mooi Plaats solar PV project in April, bringing 380 MW of the 520 MW Koruson 2 cluster into commercial operation.
Key Contracts, Suppliers and Consultants
Not stated.
Contact Details for Project Information
Anglo American South Africa Nevashnee Naicker, tel +27 11 638 3189 or email nevashnee.naicker@angloamerican.com.
EDF power solutions, tel +27 21 657 4200 or email info@edf-re.co.za.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation