Eramet halts Weda Bay Nickel production in Indonesia after mining quota runs out

Weda Bay nickel ore

Weda Bay nickel ore

4th June 2026

By: Reuters

  

Font size: - +

JAKARTA - The Indonesian unit of French miner Eramet has halted nickel ore production after a government decision to slash its 2026 mining quota by 70% compared to last year left it unable to continue operating, the company's CE said on Thursday.

Weda Bay Nickel, Eramet's nickel mining joint venture in Indonesia with China's Tsingshan Group and State miner Antam, received an initial production allowance of 12-million tons for this year, down from the 42-million tons it produced in 2025, as part of the government's efforts to better control supplies and support prices.

"The mining quota has been exhausted, so now we are in discussion with the mining ministry to get an extension of our permit," Eramet Indonesia's CE Jerome Baudelet told reporters on the sidelines of an industry conference.

Production has been suspended since late May and the company has reduced its workforce and entered into a maintenance phase.

Baudelet said revisions to mining quotas, also known as RKAB, were typically made before the end of July.

"We produced 42-million (tons) last year, so obviously we could ask for the same," he said, adding that it was ultimately the government's decision.

"We just hope they will give us enough for us to sustain the operation," Baudelet said.

The 42-million tons of nickel ore supplied by Weda Bay Nickel last year accounted for about a third of the 120-million tons processed at Indonesia Weda Bay Industrial Park, one of Indonesia's major nickel hubs.

"If we don't get an extension, then you have a deficit of 30-million tons from Weda Bay Nickel," Baudelet said.

"If you cut production and you don't give an extension, imports from the Philippines are going to increase a lot because there's not enough ore around IWIP ... it will be high cost."

Edited by Reuters

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 
ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.05 0.936s - 150pq - 2rq
Subscribe Now