Trac to wrap up new R248m Montrose interchange in 2023

Image of the OR Tambo interchange on the N4

The OR Tambo interchange

15th February 2022

By: Irma Venter

Creamer Media Senior Deputy Editor

     

Font size: - +

Trans African Concessions (Trac) says it will go ahead with the construction of the much-anticipated Montrose interchange. 

This project, valued at R248-million, officially kicked off at the beginning of this year, and will see the upgrading of the existing at-grade intersection to a grade-separated free-flow interchange.

The first phase of this project will include blasting activities to realign 600 m of the existing Schoemanskloof carriageway. 

The initiative will also include the construction of four new interchange ramps and the widening of the existing two-lane crocodile bridge from two to five lanes. 

In addition, two new arch bridges will be constructed to cross the existing Elands Valley section, and to accommodate two new ramps. 

New high-mast lighting will also be installed to illuminate the new interchange.

This project is being managed by a Wilson Bayly Holmes-Ovcon (WBHO)/Motheo JV, and is expected to take 15 months, with the provisional completion date set for June next year.

Trac says it believes that the Montrose interchange will create a free-flow, split-level interchange that will greatly improve traffic flow, similar to the two interchanges – Machado and Karino – that were recently constructed on the route.

The rehabilitation project for section 5A between Wonderfontein and Belfast will also start this month. 

Roadworks, being done under the management of Actophambili Roads and valued at R244-million, will include the rehabilitation and improvement of the existing road, which is set to be completed by December 2023.

With the start of these projects comes the conclusion of another – the upgrade between Kaapmuiden and Kaalrug in the Nkomazi region. 

This 15.5-km portion of the Maputo Corridor now has a four-lane carriageway and a rehabilitated road surface.

Emalahleni – Middelburg Road 
Noticeable progress has also been made on Trac’s other major construction projects underway on the South African side of the N4 Route, says the concessionaire.

The rehabilitation project between the OR Tambo and Van Dyksdrift interchanges in the Highveld region is 85% complete, with completion expected in March. 

The R380-million project, being built by Raubex Construction, includes removing and replacing concrete slabs from the originally constructed concrete surfaced

road, overlaying the entire section with asphalt and constructing an additional seven kilometres of passing lanes.

Belfast-Machado Rehabilitation and Upgrade
The major upgrade between Belfast and Machadodorp is progressing well and is 90% complete, notes Trac.

The R400-million project, undertaken by WBHO, includes constructing an additional lane per direction and thus upgrading this section to a four-lane road. 

A new interchange at Machadodorp was built under this project and officially opened in September.

Roadwork teams have started  an additional component of this project – the construction of the Milly’s underpass – which, together with the remaining roadworks, is scheduled for completion in June this year.

Karino Interchange
The Mbombela-based Karino interchange project is valued at R390-million and is 88% complete. 

Implemented by Raubex Construction, it constitutes the upgrading of the existing intersection into a grade-separated interchange, with on- and off-ramps. 

The project also includes a bridge that will separate cross-traffic from through-traffic to ease flow at the busy intersection. 

Although the project has experienced unforeseen delays, it is progressing steadily, with completion scheduled for March, notes Trac.

 

Edited by Creamer Media Reporter

Comments

Array

Showroom

GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 
M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.082 0.136s - 139pq - 2rq
Subscribe Now