Kibo completes MCPP integrated bankable feasibility study

23rd January 2017

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

     

Font size: - +

JOHANNESBURG (miningweekly.com) – The positive outcome of Aim- and AltX-listed Kibo Mining’s integrated bankable feasibility study (IBFS) for the Mbeya coal-to-power project (MCPP), in Tanzania, has placed the company in “a strong position” during the ongoing discussions and negotiations for the final power purchase agreement, as well as with potential projects funders and investors.

The finalised IBFS, which comprises the definitive mining feasibility study, the definitive power feasibility study, the integrated financial model for the MCPP and all other relevant technical studies completed to date, has presented a financially, technically and operationally robust project.

“We are extremely pleased with the positive results from the IBFS. The significant improvement in the various internal rate of return (IRR) figures exceeds management expectations and will, without doubt, attract favourable attention from potential investors,” said Kibo CEO Louis Coetzee.

Kibo is engaged in “highly confidential discussions” with various parties, including regulatory authorities, and it will limit the amount of details from the study it releases publicly until the conclusion of the talks.

The completed report shows the MCPP can be built and commissioned within the previously projected duration of 36 months, with a 21.1% reduction on the total capital requirements originally laid out in the integrated prefeasibility study for the integrated project.

The Tanzania-focused mineral exploration and development company said the latest results also indicated total revenue over an assumed 25-year project life of about $7.5-billion to $8.5-billion.

There are also sufficient additional coal resources available from the Mbeya coal mine to expand the power station to more than double the current design size and plant life, while the technical and environmental risk assessment confirms the construction-ready state of the project, with no environmental “red flags”.

The IBFS further shows an 11% increase on the indicative post-tax equity IRR to between 21% and 22%.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Latest Multimedia

Photo of Martin Creamer
On-The-Air (08/05/2026)
Updated 2 hours 20 minutes ago By: Martin Creamer

Showroom

Lion Alcolmeter® 700
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 
ASTPM
ASTPM

Established in 1983, the ASTPM is an industry association and representative body of the welded carbon steel tube and pipe manufacturers of South...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 08 May 2026
Magazine round up | 08 May 2026
8th May 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.054 0.088s - 140pq - 2rq
Subscribe Now