Isang substation project, Botswana
Name and Location
Isang substation project, Botswana.
Project Description
The project involves the construction of a new 400/220-kV substation to be located about 40 km from Gaborone, in Botswana. The facility will help support the integration of electricity generated by the 600-MW Morupule B power plant into the country's national grid. In addition, the unit will electrify some 100 villages and several other villages experiencing severe power shortages.
The project also includes the construction of a 400-kV transmission line from the Morupule B power station to the Isang substation.
Value
The value has not been disclosed.
Duration
The project is scheduled for completion in 2011.
Client
Botswana Power Corporation (BPC).
Key Contracts and Suppliers
ABB (construction) and African Development Bank (finance).
Latest Developments
ABB has been awarded a contract to design, supply, install and commission the Isang substation project.
The firm will supply eight fully equipped 400-kV and 220-kV bays at the project site. The substation will be the first in the region to be equipped with an IEC 61850-compliant automation, control and protection system. The system ensures interoperability and open communications between substation devices and other grid installations.
On Budget and on Time?
Too early to state.
Contact Details for Project Information
ABB senior communications specialist Eubulus Pillay, tel +27 10 202 5770,fax +27 11 579 8364 or email eubulus.pillay@za.abb.com.
BPC, tel +267 360 3203, fax +267 397 3563; or Dennis Olaotse, email OlaotseD@bpc.bw.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation