Name of the Project
Trianel Borkum II wind farm project.

Location
The Trianel Borkum II wind farm is planned to be installed 45 km north of Borkum Island, in the German North Sea.

Client
Trianel Windkraftwerk Borkum II.

Project Description
The offshore project will consist of 32 tur-bines and will have an installed capacity of about 203 MW.

The turbines will be installed in water 25 m to 35 m deep.

Jobs to be Created
Not stated.

Value
Not stated.

Duration
The project is expected to be completed in 2019.

Latest Developments
Senvion has been awarded a contract to deliver the offshore turbines for the wind farm. The contract comprises 32 Senvion 6.2M152 turbines, which will produce an estimated 800-million kilowatt hours of electricity a year and enough to supply about 210 000 households a year.

Key Contracts and Suppliers
Senvion (wind turbines).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Trianel Windkraftwerk Borkum II press contact Maik Hünefeld, tel +49 241 413 20 282 or email m.huenefeld@trianel.com.
Senvion press contact Verena Puth, tel +49 40 5555 090 3051 or email verena.puth@senvion.com.