Solar power generation and battery energy storage system project, Mongolia

4th June 2021 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Solar power generation and battery energy storage system project, Mongolia

Name of the Project
Solar power generation and battery energy storage system (BESS) project.

Location
Uliastai, Zavkhan province, in Mongolia.

Project Owner/s
Ministry of Energy of Mongolia.

Project Description
The project forms part of the Upscaling Renewable Energy Sector project, which aims to expand the use of renewable energy in Mongolia.

The project involves the construction of a solar power generation system with a capacity of 5 MW, a BESS with a capacity of 3.6 MWh and an energy management system.

Potential Job Creation
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
The project is expected to be completed in 2022.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
JGC Corporation, NGK Insulators and MCS International (construction contract).

Contact Details for Project Information
Ministry of Energy of Mongolia, tel +976 7700 8544.