Schneider Electric and Senwes with Motla partnership ensure consistent and safe energy supply

14th June 2022

Senwes, one of South Africa’s leading agricultural companies has partnered with Schneider Electric for an ambitious substation upgrade project that now sees the organisation benefiting from accessible, advanced and a stable electricity supply.

The Senwes Group of companies operate nationally.  Unfortunately, the Senwes’ Head Office, based in Klerksdorp in the North West, had been experiencing energy supply issues due to its dedicated substation’s aging infrastructure which included faulty switchgear.  The substation is owned by the City of Matlosana municipality.

Motla Consulting Engineers has been supporting Senwes in a Strategic Technology Development Partnership for many years. To remedy the issue, Senwes and Motla decided to upgrade and move the substation that would ensure its Klerksdorp offices and surrounds benefit from safe and efficient energy supply based on advanced technology that could be managed from outside the confines of a building.

Digitalistion with the use of connected devices has been identified by Senwes and Motla as one of the key development areas for any new installations.  “The Internet of Things, a world where value-add for business is unlocked by analyzing and utilizing information to make the business more efficient and more profitable", is the direction for the future, says Chris Lombard, Managing Director for Motla Consulting Engineers.

Schneider, as a long-term Technology Development Partner for Senwes, and with world leading products for the application, was engaged as technology supplier for this project.

“Following extensive and lengthy negotiations with the City of Matlosana, it was decided to not only upgrade the substation but also move it to a safer environment. Senwes’ basement at its Klerksdorp offices offered a safe and practical choice,” explains Llewellyn Bakker, Application Design Engineer. Power Systems Division at Schneider Electric.

The installation and benefits

Once the City of Matlosana gave the go ahead (for the substation to be moved), the installation process commenced in earnest and ran smoothly. The teams from both Senwes and Motla regularly met with Schneider Electric to ensure that not only the correct equipment was installed (for underground usage) but the current and aging substation was moved safely.

The project rollout on site was executed by Einstein Electrical. It took 80 days for the complete  installation of the substation with a state-of-the-art Premset medium voltage (MV) switchgear solution from Schneider Electric.

“New, advanced equipment was installed and made feature ready, therefore, enabling Senwes to among others access switchgear from outside the substation. This enables Senwes to constantly monitor power ratings and substation conditions,” says Thabang Pitso, Project and Application Designer, Power Systems Division, Schneider Electric.

As Mr Johann Becker from Senwes testified; "With the newly installed equipment we have significantly reduced the risks for safety, reliability and consequential damages associated with the old switchgear.  We now also have better monitoring and operating capabilities with the connected switching devices."

The Senwes’ Head Offices in Klerksdorp and surrounding utility users now benefit from:

Schneider Electric also installed a 19-inch HMI (Human Machine Interface) to allow the substation operators to manage the status of the breakers which adds another level of safety. Additionally, the substation solution has been setup to allow the operators to address issues on their own without the help of Schneider Electric. 

Concludes Bakker: “The Senwes Klerksdorp substation now provides consistent, regulated, and automated supply. Fault finding has also been simplified and the infrastructure can be monitored to ensure potential issues are timeously identified and remedied.”