Musina ring road project set for 2022 completion

13th August 2021 By: Irma Venter - Creamer Media Senior Deputy Editor

The R640-million Musina ring road project is set for completion in the second quarter of next year, says the South African National Roads Agency Limited (Sanral).

The road will alleviate traffic congestion in the Musina central business district (CBD) and reduce travel time for road users in and around the Limpopo town.

The project involves the construction of about 8 km of a greenfield single- carriageway freeway to form the western ring road around the town.

The alignment deviates from the existing N1 section 29 alignment just south of Musina, and ties back into the existing alignment just north of the town.

Thousands of heavy vehicles use the N1 every day and pass through the Musina CBD, says Sanral.

These vehicles add to the traffic congestion in the town, while also creating conflict with local traffic and pedestrians.

“Once completed, the Musina ring road will facilitate mobility, and the safe movement of goods and services in and around Musina,” says Sanral project manager Hennie Kotze.

He says the project is progressing well.

The stormwater infrastructure is complete, as are the majority of the earthworks.

Except for the Nancefield interchange bridge, the other bridges are at advanced stages of completion.

The contractor is currently progressing with layer works and surfacing.

“Apart from Covid-19-related restrictions, which are proving to be a challenge not on the Musina ring road project alone, but on other projects managed by Sanral across the country, we are confident about the anticipated June 2022 completion date, provided there are no further delays,” says Kotze.

The project has provided opportunities for a number of local community members and small, medium-sized and microenterprises, he adds.

Fourteen targeted enterprises from the Musina municipal area are currently employed to participate in the project.

Up to 12% of the R640-million contract value is allocated to targeted enterprises, of which 10% is allotted to women-owned companies, says Kotze.

“The contractor has exceeded the 12% [target] and is currently standing at 14%.”