POWERLESS:

19th July 2013 By: Darlene Creamer

POWERLESS:

Eskom has set the second half of 2014 as the new “realistic” deadline for synchronising Medupi’s first unit, Unit 6, to the grid. The announcement followed an independent assessment of the schedule and fresh delays to the control and instrumentation contract. The utility also confirmed that the cost of the project has increased from R91.2-billion to R105-billion, excluding interest during construction.