Name of the Project
Oriana solar project.

Location
Victoria County, in Texas, US.

Project Owner/s
Sabanci Renewables.

Project Description
The project involves the design and construction of 232 MWdc solar project and the construction of a 60 MW energy storage facility.

The plant is expected to produce enough clean energy to power more than 34 000 homes. It will include highly efficient bifacial solar panel technology that enables both sides of the panels to absorb sunlight.

The renewable power produced will be delivered to customers on the grid managed by the Electric Reliability Council of Texas.

Potential Job Creation
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
Construction is expected to start in early 2024 and be completed by mid-2025.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
Bechtel (engineering, procurement, construction, commissioning and project management).