Name of the Project
Nhon Trach 3&4 power plant.

Location
Ong Keo Industrial Park, in the Nhon Trach district, Vietnam.

Project Owner/s
PetroVietnam Power Corporation (PV Power).

Project Description
Nhon Trach 3&4 involves the construction of a combined-cycle gas-fired power plant.

This project will contribute to the implementation of Vietnam’s announced commitment to achieving net-zero carbon emissions by 2050 by supporting the rapid expansion of renewable energy through its dispatchable power profile.

The power plant is expected to deliver more than 1.6 GW of electricity, and it will be the first power plant fuelled by liquefied natural gas in the country.

The project will include a gas turbine, a steam turbine, a generator, a once-through heat recovery steam generator and a control system.

Potential Job Creation
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
The project is expected to come into commercial operation in 2025.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
Samsung C&T Corporation (engineering, procurement and construction) and General Electric (gas turbine).

Contact Details for Project Information
PV Power, tel +84 24 2210288.