Matola drybulk terminal expansion, Mozambique

29th April 2022 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Matola drybulk terminal expansion, Mozambique

Name of the Project
Matola drybulk terminal expansion.

Location
Port of Maputo, Mozambique.

Project Owner/s
Matola Terminal Joint Venture (JV) comprising Grindrod and Vitol.

Project Description
Matola Terminal JV plans to expand the capacity of the Matola drybulk terminal from the current 7.3-million tons a year to more than 12-million-tons year.

Potential Job Creation
Not stated.

Capital Expenditure
Grindrod’s share is estimated at R1.8-billion.

Planned Start/End Date
The project is expected to be completed by the fourth quarter. The procurement of the shiploader will start shortly thereafter.

Latest Developments
Work on the expansion project has started, specifically to understand the ability of the quay to accommodate a second shiploader.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Grindrod, tel +27 31 304 1451 or email grindrod@grindrod.com.