Koeberg nuclear power station steam-generator replacement project, South Africa – update

5th August 2022 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Koeberg nuclear power station steam-generator replacement project, South Africa – update

Photo by: Bjorn Rudner

Name of the Project
Koeberg nuclear power station steam-generator replacement (SGR) project.

Location
Western Cape, South Africa.

Project Owner/s
Eskom.

Project Description
The current steam generators in Unit 1 and Unit 2 at the Koeberg nuclear power station have been in operation since 1984 and 1985 respectively. The aim of the project is to extend the design life of the nuclear power station by 20 years to 2045.

The project involves the replacement of all six steam generators for units 1 and 2.

The SGR project involves the design, manufacture and installation of three steam generators in each of the Koeberg power plant’s two operating units, as well as safety analyses and studies to comprehensively demonstrate the plant’s design integrity, with no adverse impact on public and worker safety and health or the environment, including the enhancement of nuclear safety.

The new generators will incorporate modern design features for easy maintenance and inspections, and improve heat-transfer efficiency, leading to an overall efficiency improvement of Koeberg.

The installation of the generators will be conducted during the scheduled refuelling, inspections and maintenance outages of the two units at Koeberg power station. Eskom is on track and progressing according to plan for installation during the next unit 1 and 2 outages.

The other major components of the life-extension plan include:

This safety case on the life extension will be presented to the National Nuclear Regulator in mid-2022 to allow for approval of the Koeberg plant’s entering into long-term operation from mid-2024.

Capital Expenditure
Not stated.

Planned Start/End Date
Work on replacing the steam generators for the first of Koeberg’s two units is scheduled to start during a planned outage in January 2022, with the overall project taking two years to complete.

Latest Developments
South Africa’s National Nuclear Regulator (NNR) confirmed on July 27 that Eskom had submitted the safety case in support of its application to extend the operational life of the Koeberg nuclear power station beyond the current licence term.

Eskom is finalising the public information document and will have to publish the application and the public information document in the Government Gazette and newspapers, and serve notices to interested and affected parties.

Key Contracts, Suppliers and Consultants
Framatome (main SGR contractor); General Electric (modifications to the balance of plant or secondary turbine system); and Jacobs Engineering (BoP hardware changes).
 
Contact Details for Project Information
Eskom media desk, email mediadesk@eskom.co.za.