Kenmare WCP B relocation under way in Mozambique

15th September 2020 By: Tasneem Bulbulia - Senior Contributing Editor Online

The relocation of the Wet Concentrator Plant (WCP) B at Kenmare Resources' Moma titanium minerals mine, in northern Mozambique, is under way.

Kenmare previously announced three development projects that, together, have the objective of increasing yearly ilmenite production to 1.2-million tonnes (plus co-products) on a sustainable basis from 2021, with the move of WCP B to the high-grade Pilivili ore zone being the final project.

The increased production is expected to significantly lower cash operating costs to between $125/t and $135/t.

Consequently, from 2021, the group expects to be positioned in the first quartile of the industry revenue to cost (or margin) curve, supporting stronger free cash flow generation and providing for increased shareholder returns.

WCP B is being moved 23 km from its previous mining area at Namalope to a new high-grade ore zone called Pilivili. It is being transported along a purpose-built road using platform vehicles called self-propelled modular transporters (SPMTs).

The relocation of WCP B and its dredge is being undertaken by a global specialist heavy lifting and transport contractor.

Mining at Namalope was completed in late August.

The WCP B and its associated dredge have now been successfully placed on the concrete plinths in the relocation pond and the pond has been dewatered.

The dredge and the WCP B are to be moved in two stages. The first stage involves the movement of the dredge, which is expected to be completed this week.

Once the dredge has been relocated to Pilivili, the SPMTs will return to Namalope to transport the WCP B along the same route. The physical relocation is expected to be completed in the next few weeks.

"The relocation of WCP B and its dredge form the third and final project of our development programme to increase Moma’s ilmenite production to 1.2-million tonnes per annum on a sustainable basis.

"Once WCP B and the dredge reach Pilivili we will begin the process of re-establishing them in their new location and we expect mining to commence at Pilivili during quarter four 2020,” says MD Michael Carvil.