Interstate-35E project – Phase 2, US

17th September 2021 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Interstate-35E project – Phase 2, US

Name of the Project
Interstate- (I-) 35E project – Phase 2.

Location
From I-635, in Dallas, to the Denton County line in Carrollton, Texas, in the US.

Project Owner/s
Texas Department of Transportation (TxDOT)

Project Description
The project entails the design, construction and maintenance of Phase 2 of the project.

The 10 km design-build project includes the full reconstruction and expansion of six existing general-purpose lanes to eight general-purpose lanes, with new auxiliary lanes at entrance and exit ramps, and the reconstruction of frontage roads along the corridor.

The project also includes the reconstruction of the two existing, grandfathered reversible tolled-managed lanes.

Potential Job Creation
Not stated.

Capital Expenditure
The contracts are valued at $640-million.

Planned Start/End Date
Construction is scheduled to begin in late 2021, with substantial completion expected in late 2025.

Latest Developments
The TxDOT awarded Austin Bridge & Road, and Fluor the contract to design, construct and maintain Phase 2 of the I-35E project.

Key Contracts, Suppliers and Consultants
Austin Bridge & Road and Fluor (design, construction and maintenance – Phase 2).