Name of the Project
I-37 reconstruction project.

Location
San Patricio County, Texas, in the US.

Project Owner/s
Texas Department of Transportation (TxDOT).

Project Description
The scope of work includes the direct connectors at the intersection of I-37 and US 77, and upgrades to the existing main lanes.

The project includes the construction of additional auxiliary lanes, which will increase the capacity of the road in the event of a hurricane or other emergency evacuation.

Major work activities comprise the demolition and construction of bridges over the Nueces river, I-37 North and a frontage road overpass.

Potential Job Creation
Not stated.

Capital Expenditure
The contract valued at $84-million.

Planned Start/End Date
The project is scheduled to last about 65 months, with construction expected to start in September 2021.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
Ferrovial subsidiary Webber (reconstruction contract).

Contact Details for Project Information
TxDOT, tel +1 512463 8588.