Gas separation plant, Kazakhstan

5th March 2021 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Gas separation plant, Kazakhstan

Name of the Project
Gas separation plant.

Location
Kazakhstan.

Project Owner/s
The project is being implemented by KazMunayGas and its subsidiary KLPE.

Project Description
The project calls for KLPE to build a gas separation plant, with a capacity of 957-milion standard cubic feet a day, adjacent to a plant run by Tengiz Oilfield development company Tengizchevroil – a joint venture between ExxonMobil, Chevron, KazMunayGa and others).

The separated ethane will be supplied as raw material for a further planned plant for manufacturing polyethylene.

Potential Job Creation
Not stated.

Capital Expenditure 
Not stated.

Planned Start/End Date 
Not stated.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
JGC Holdings Corporation (front-end engineering design).

Contact Details for Project Information
KazMunayGas,+ 7 (7172) 78 61 01