East Anglia Hub, UK

16th July 2021 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

East Anglia Hub, UK

Name of the Project
East Anglia Hub.

Location
North Sea, UK. East Anglia THREE will be located 69 km off the Norfolk coast, near the London metropolitan area.

Project Owner/s
Iberdrola, through its UK subsidiary ScottishPower Renewables.

Project Description
Iberdrola plans to build a macro offshore wind farm comprising three projects – East Anglia ONE North (800 MW), East Anglia TWO (900 MW) and East Anglia THREE (1 400 MW), for a total capacity of 3 100 MW.

This power is enough to supply clean energy to 2.7-million UK homes.

Potential Job Creation
The projects will create a pipeline of continued economic investment that will support jobs and opportunities across the east of England.

Capital Expenditure
£6.5-billion.

Planned Start/End Date
The offshore wind farms will be developed simultaneously, which will shorten construction and commissioning times.

Construction of the East Anglia Hub is expected to start in 2023 and finish in 2026.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
Siemens Gamesa Renewable Energy (preferred supplier – wind turbines).

Contact Details for Project Information
Iberdrola corporate communication, tel +34 91784 3232 or email communicacioncorporativa@iberdrola.es.