Dolna Odra power plant, Poland

5th June 2020 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Dolna Odra power plant, Poland

Name of the Project
Dolna Odra power plant.

Location
The project is located in the Western Pomerania region of Poland.

Project Owner/s
Polska Grupa Energetyczna Górnictwo i Energetyka Konwencjonalna (PGE).

Project Description
Dolna Odra will be a higher-efficiency and lower-emission power plant, which is expected to reduce carbon dioxide emissions by about 2.3-million tonnes a year.

The project comprises the construction of a combined-cycle 1.4 GW power plant that will produce the equivalent electricity needed to power about one-million Polish households, while meeting the most rigorous environmental standards for emissions.

The power plant will comprise two gas turbines and two steam turbines.

Potential Job Creation
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
The plant is expected to be commissioned in 2023.

Latest Developments
None stated.

Key Contracts and Suppliers
GE (gas and steam turbines).

Contact Details for Project Information
PGE, tel +48 44 737 73 00 or email kancelaria.giek@gkpge.pl.