Name of the Project
Crystal Brook Energy Park.
Location
South Australia.
Project Owner/s
Renewable-energy company Neoen.
Project Description
Crystal Brook Energy Park is a hybrid renewable-energy project that can provide reliable, 24-hour power for South Australian consumers.
The project will combine about 235 MW of wind and solar generation, 130 MW/400 MWh of battery storage, and will produce 25 t/d of hydrogen.
Potential Job Creation
Not stated.
Capital Expenditure
€370-million.
Planned Start/End Date
Completion is expected in 2024.
Latest Developments
None stated.
Key Contracts, Suppliers and Consultants
None stated.
Contact Details for Project Information
Crystal Brook Energy Park, email crystal@brookenergypark.com.au.