Contractors may need clauses to mitigate exceptional international events

16th March 2022 By: Tasneem Bulbulia - Senior Contributing Editor Online

Having barely survived the negative economic effects of Covid-19, South African construction contractors now need to factor in the risk of massive price hikes following the war in Ukraine and resultant sanctions against Russia, says construction law firm MDA Attorneys.

The law firm notes that contractors may need to mitigate risks by including a clause in contracts to make provision for exceptional international events, as there is no such appropriate clause in standard form contracts.

“There is no reasonable way for contractors to factor the effects of exceptional international events into their contract prices, neither would it be reasonable to expect a contractor to do so. Without clarity, contractors run the risk of being unable to complete the works or completing them at a loss,” says MDA Attorneys associate Tamlynn Caelers-Avis.

Force majeure clauses are applicable to events which are unforeseeable and could, therefore, not have been provided for at the time of entering into the contract. These clauses in standard form contracts would not assist contractors currently negotiating and entering into contracts that may be impacted as a result of the Ukraine war.

In addition, force majeure clauses generally deal with the time implications of an unforeseeable event; it is only certain contracts which provide for payment of the associated costs and in specific circumstances, MDA Attorneys explains.

It notes that price spikes and shortages are already being reported in the South African construction industry – personnel, goods, supplies and materials – and the situation is unlikely to be immediately resolved.

“Exactly what the next exceptional international event may be is unpredictable and so are the ripple effects of these type of events. To mitigate this risk for contractors, MDA Attorneys has drafted a clause to deal with exceptional international events.

“An exceptional international event clause creates a mechanism for the parties to discuss how cost spikes will be dealt with. Contractors notify the commissioning party (employer) of price fluctuations to find an appropriate and reasonable way forward which does not unfairly skew the risk allocation,” Caelers-Avis says.

Construction contracts require parties to cooperate to achieve completion of the works, and Caelers-Avis says this implies that employers should be cognisant of the possibility of impacts.

Should there be a dispute related to increased costs, the general dispute process outlined in the contract applies. 

“Since we focus specifically on the construction sector, we are engaging with clients and parties to find a workable way forward,” she says.