Calidus looks at solar solutions for Warrawoona

24th January 2022 By: Esmarie Iannucci - Creamer Media Senior Deputy Editor: Australasia

PERTH (miningweekly.com) – Gold developer Calidus Resources has inked an agreement with Zenith Pacific for the construction of a 4 MW solar farm with 3.5 MW battery energy storage system at its Warrawoona gold project, in Western Australia.

Zenith is currently constructing the 11 MW gas-fired power station at Warrawoona under a power purchase agreement (PPA). The construction of the solar farm is part of the PPA whereby Calidus purchases power from Zenith.

The solar farm will be constructed in the second half of 2022 and will feed into the distribution line between the power station and accommodation village.

Calidus MD Dave Reeves said the decision to proceed with the solar farm and battery storage was in line with the company’s environmental, social and governance (ESG) initiatives.

“Calidus is committed to carbon reduction as part of its ESG policy. This renewable microgrid is a cornerstone to our carbon reduction plan which includes the use of liquefied natural gas (LNG) not diesel and the ability of the LNG gensets to use up to 25% hydrogen. We are pleased to extend the relationship with Zenith to incorporate this renewables project, and look forward to its construction in the second half of this year,” Reeves said.

Warrawoona is expected to produce up to 105 000 oz of gold a year, but could potentially produce up to 139 000 oz/y when the nearby Blue Spec deposit is developed.