Berg River Voëlvlei Augmentation Scheme, South Africa

10th September 2021 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Berg River Voëlvlei Augmentation Scheme, South Africa

Name of the Project
Berg River Voëlvlei Augmentation Scheme (BRVAS).

Location
In the Western Cape, South Africa.

Project Owner/s
The Trans-Caledon Tunnel Authority (TCTA) will fund and implement the BRVAS project on behalf of the Department of Water and Sanitation. The water users will include the City of Cape Town metropolitan municipality, the Drakenstein district municipality, the Bergrivier, Saldanha Bay, Swartland and Stellenbosch local municipalities, as well as the Lower Berg Irrigation Board, besides others.

Project Description
The BRVAS has been designated a Strategic Integrated Project by the Presidential Infrastructure Coordinating Commission.

BRVAS will abstract water from the Berg river in winter and pump it to the existing Voëlvlei dam. The new scheme will augment the yield of the water supply system by about 23-million cubic metres a year. The project comprises:

To be determined during the construction tender process.

Capital Expenditure
The project is estimated at R1-billion, excluding value-added tax.

Planned Start/End Date
The construction tender process is planned to start in early 2022.

Latest Developments
A laboratory hydraulic model study has been successfully completed and the detailed geological and geotechnical investigations have started.

Key Contracts, Suppliers and Consultants
Amanzi Entaba Joint Venture, or AEJV, a joint venture between Bigen Africa Group Holdings, Nyeleti Consulting and Gibb Holdings (consulting services).

Contact Details for Project Information
TCTA, tel +27 12 683 1200 or email ​info@tcta.co.za.