Arenastaden zero energy hotel, Sweden

18th April 2019 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Arenastaden zero energy hotel, Sweden

Name of the Project
Arenastaden zero energy hotel.

Location
The project will be located in Arenastaden, Sweden.

Project Owner/s
Fabege.

Project Description
The project entails the construction of Scandinavia’s first zero energy hotel.

The project consists of about 22 400 m2, comprising 11 floors, 336 rooms, 88 apart­ments for long-term accommodation and the Nordic Choice Hotels Swedish headquarters.

The hotel will feature an estimated 21 geo­thermal energy boreholes, along with almost 1 800 m2 of solar panels on the roof and 1 000 m2 on the façade, which will produce more energy than the property will consume.

Potential Job Creation
Not stated.

Capital Expenditure
SKr470-million.

Planned Start/End Date
Construction has started and the new hotel is scheduled for completion during the first quarter of 2021.

Latest Developments
Skanska has signed a contract with Fabege to build the hotel.

Key Contracts and Suppliers
Skanska (construction contract).

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Fabege project manager Maria Jansson, tel +46 8 555 148 96 or email Maria.Jansson@fabege.se.
Fabege communicator projects, Annica Bergman, tel +46 8 556 747 98 or email Annica.Bergman@fabege.se.