Tunnelling works at Lesotho Highlands Water Project progressing

6th November 2020

By: Simone Liedtke

Creamer Media Social Media Editor & Senior Writer

     

Font size: - +

Underground tunnelling works inside the two Polihali diversion tunnels are progressing well, with excavations advancing from the outlets at about 6 m a day per tunnel at the Lesotho Highlands Water Project (LHWP) site.

So far, the excavation of the intake and outlet portals has been completed and work on the tunnels’ concrete lining is under way, with concrete casting and reinforcement having started on tunnel one. Both tunnels’ intake and outlet portal drives have been supported with sprayed concrete and rock bolts and preparatory works for the concrete inlet structure also ongoing.

This is despite a slow start in May, owing to extended Covid-19 restrictions, which impacted on shift work and reduced the number of workers on site to enable physical distancing.

Continued border restrictions between Lesotho and South Africa posed travel challenges for technicians and also affected the movement of equipment and supplies from South Africa.

The tunnels (one 7 m in diameter and almost 1 km long, and the second 9 m in diameter and also almost 1 km long) run parallel to each other from the intake point to the outlet downstream of the dam.

The tunnels are being excavated in advance of the construction of the Polihali dam to shorten the dam construction period. Impoundment of the Polihali reservoir is expected to start in 2024, with water delivery planned to start in 2027.

“As construction picks up on the diversion tunnels, the teams continue to observe the Lesotho Highlands Development Authority's (LHDA’s) strict health and safety protocols to ensure that the work environment is safe for crews.

"These protocols include airborne contaminant monitoring; monitoring of the excavation works, rock support and work-area temperature; and monitoring of air flow, among other measures. The project invests heavily in safety measures, hence the installation of ventilation fans inside the tunnels in August,” says LHDA CE Tente Tente.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION