Teck reduces coal output rate and suspends 2020 guidance

1st April 2020

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Notwithstanding the challenges related to the fast-spreading coronavirus, Canadian diversified miner Teck Resources president and CEO Don Lindsay on Wednesday reported that all the group’s operations remained in production, albeit on a reduced basis.

The Vancouver-headquartered group announced that it had slowed operations and reduced its crews by up to 50% of regular levels at its steelmaking coal operations and Highland Valley Copper operations, in British Columbia, in response to the Covid-19 pandemic.

These measures started on March 25 and would be in place for an initial two-week period.

At the Trial Operations, also in British Columbia, the number of employees on site had been reduced by one-third, while production continued at planned rates.

While production levels would vary from site to site, Teck’s overall steelmaking coal production would be reduced to between 80% and 85% of normal levels during the initial two-week period.

This comes as the miner reported better-than-expected results from the steelmaking coal unit, which had a rough start to the year, with sales threatened by heavy rain, snow and mudslides.

But Teck on Tuesday reported that results in the steelmaking coal unit improved significantly in late February and March, with first-quarter sales estimated at 5.6-million tonnes, exceeding its guidance of 4.8-million to 5.2-million tonnes.

At the same time, it expected adjusted site costs of sales of about $65/t, which would be “well below” previous expectations.

Further, in spite of a difficult start to the year, the steelmaking coal logistics supply chain performed well for the remainder of the quarter, with CP and CN recovering from early weather-related disruptions and blockades.

“All three ports also performed well, in particular Westshore Terminals, which had a strong March,” said Teck.

Regarding capital projects, the miner said that the Neptune facility upgrade continued to advance and major equipment deliveries were on track.

“We expect the new shiploader, stacker/reclaimer, and single dumper replacement to be commissioned around year-end. Completion of construction is still expected in the first quarter of 2021, with the new double dumper expected to be commissioned in the second quarter of 2021.”

The shutdown at the Elkview Operations to complete the plant expansion from seven-million tonnes to nine-million tonnes was also progressing and would be completed by mid-April.

The upgrade would enable Teck to replace higher cost production from the soon-to-be-closed Cardinal River mine, which produced 1.4-million tonnes in 2019, with lower cost production from Elkview, bolstering earnings by about $110-million a year.

Meanwhile, at Red Dog, in the US state of Alaska, zinc production remained at planned levels, despite significant travel restrictions and modified schedules required to maintain safe operations due to the fly-in, fly-out nature of the operation.

In Peru, the Antamina mine continued to operate at full production levels with less than half of the normal workforce.

At Carmen de Andacollo in Chile, full production had also been maintained to date with reduced workforce levels. Construction of the QB2 project, in Chile, remained suspended.

Citing the high degree of uncertainty associated with the current Covid-19 crisis, Teck suspended its guidance for 2020.

“Covid-19 has the potential to affect both our customers and certain of our suppliers, and we are closely monitoring potential impacts on demand for our products, as well as our supply chain.

"Our operating plans will depend in part on regulatory restrictions that may affect our business, as well as the progress of the pandemic generally, and the extent of additional measures, if any, required to protect the health and safety of employees. The actual degree and duration of production slowdowns and/or staff reductions and related costs is unknown at this time,” said the company.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION